PK0-005 · Question #552
During the planning phase, a project manager has gathered all necessary information and must now draft a document outlining the objectives, deliverables, milestones, constraints, and justifications…
The correct answer is B. Scope statement. A scope statement outlines the project’s objectives, deliverables, milestones, constraints, and justifications, serving as a foundational document for project planning and execution.
Tools and documentation
Question
During the planning phase, a project manager has gathered all necessary information and must now draft a document outlining the objectives, deliverables, milestones, constraints, and justifications for the project. Which of the following should the project manager draft?
Options
- AInitial risk assessment
- BScope statement
- CWork breakdown structure
- DRelease plan
How the community answered
(46 responses)- A2% (1)
- B89% (41)
- C4% (2)
- D4% (2)
Explanation
A scope statement outlines the project’s objectives, deliverables, milestones, constraints, and justifications, serving as a foundational document for project planning and execution.
Topics
#Project planning#Scope management#Project documentation#Scope statement