CompTIA
PK0-005 · Question #499
Some project deliverables are behind schedule because adequate resources are not available to finish tasks in the set timeline. Which of the following should the project manager use to document this i
The correct answer is B. Issue log. An issue log is used to document problems that are currently affecting the project, such as resource shortages causing schedule delays. It helps track the issue, assign responsibility, and plan resolutions.
Tools and documentation
Question
Some project deliverables are behind schedule because adequate resources are not available to finish tasks in the set timeline. Which of the following should the project manager use to document this in formation?
Options
- ATime-tracking tools
- BIssue log
- CStatus report
- DTask board
How the community answered
(27 responses)- A4% (1)
- B81% (22)
- C4% (1)
- D11% (3)
Explanation
An issue log is used to document problems that are currently affecting the project, such as resource shortages causing schedule delays. It helps track the issue, assign responsibility, and plan resolutions.
Topics
#Issue log#Project documentation#Project management tools#Issue management