Question
A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?
Options
- ADefine access requirements.
- BDevelop a transition plan.
- CCreate a responsibility assignment matrix.
- DCreate a work breakdown structure.