PK0-005 · Question #421

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

The correct answer is B. Project charter. The project charter is a foundational document that outlines the project's objectives, scope, stakeholders, and overall goals. It serves as a reference point throughout the project lifecycle. By consulting the project charter during the closure meeting, the project manager can…

Tools and documentation

Question

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

Options

  • AWork breakdown structure
  • BProject charter
  • CQuality plan
  • DSolution design

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    71% (25)
  • C
    9% (3)
  • D
    17% (6)

Explanation

The project charter is a foundational document that outlines the project's objectives, scope, stakeholders, and overall goals. It serves as a reference point throughout the project lifecycle. By consulting the project charter during the closure meeting, the project manager can verify whether the project's outcomes align with the initially agreed-upon objectives, facilitating resolution of stakeholder disagreements.

Topics

#Project Charter#Project Closure#Stakeholder Alignment#Project Objectives