PK0-005 · Question #421
During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?
The correct answer is B. Project charter. The project charter is a foundational document that outlines the project's objectives, scope, stakeholders, and overall goals. It serves as a reference point throughout the project lifecycle. By consulting the project charter during the closure meeting, the project manager can…
Question
During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?
Options
- AWork breakdown structure
- BProject charter
- CQuality plan
- DSolution design
How the community answered
(35 responses)- A3% (1)
- B71% (25)
- C9% (3)
- D17% (6)
Explanation
The project charter is a foundational document that outlines the project's objectives, scope, stakeholders, and overall goals. It serves as a reference point throughout the project lifecycle. By consulting the project charter during the closure meeting, the project manager can verify whether the project's outcomes align with the initially agreed-upon objectives, facilitating resolution of stakeholder disagreements.