A product manager is producing a project status report for key stakeholders. Which of the following should most likely be included? (Choose two.)

The correct answer is B. Financial summary C. Project schedule. Financial summary: Stakeholders need to understand the budget status, including costs incurred, budget remaining, and any financial variances. Project schedule: A project schedule gives stakeholders insight into the timeline, milestones achieved, and upcoming deadlines.

Tools and documentation

Question

A product manager is producing a project status report for key stakeholders. Which of the following should most likely be included? (Choose two.)

Options

  • AFeedback
  • BFinancial summary
  • CProject schedule
  • DOrganizational chart
  • EApproval
  • FRisks

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    72% (21)
  • D
    3% (1)
  • E
    3% (1)
  • F
    14% (4)

Explanation

Financial summary: Stakeholders need to understand the budget status, including costs incurred, budget remaining, and any financial variances. Project schedule: A project schedule gives stakeholders insight into the timeline, milestones achieved, and upcoming deadlines.

Topics

#Project reporting#Status reports#Financial management#Schedule management