The correct answer is B: Financial summary. Financial summary: Stakeholders need to understand the budget status, including costs incurred, budget remaining, and any financial variances. Project schedule: A project schedule gives stakeholders insight into the timeline, milestones achieved, and upcoming deadlines.
Question
A product manager is producing a project status report for key stakeholders. Which of the following should most likely be included? (Choose two.)
Options
- AFeedback
- BFinancial summary
- CProject schedule
- DOrganizational chart
- EApproval
- FRisks
Explanation
Financial summary: Stakeholders need to understand the budget status, including costs incurred, budget remaining, and any financial variances. Project schedule: A project schedule gives stakeholders insight into the timeline, milestones achieved, and upcoming deadlines.