PK0-005 · Question #373
During the testing process, testers have found multiple bugs that could jeopardize the project commitment date. Which of the following tools should the project manager use first to update the findings
The correct answer is C. Issue log. An Issue Log is used to document any problems or issues that arise during the project execution phase, including bugs, that could affect the project's objectives such as deadlines. Since the testers found multiple bugs that could jeopardize the commitment date, they should be rec
Question
During the testing process, testers have found multiple bugs that could jeopardize the project commitment date. Which of the following tools should the project manager use first to update the findings?
Options
- ADefect log
- BChange log
- CIssue log
- DRisk log
How the community answered
(25 responses)- A4% (1)
- B16% (4)
- C76% (19)
- D4% (1)
Explanation
An Issue Log is used to document any problems or issues that arise during the project execution phase, including bugs, that could affect the project's objectives such as deadlines. Since the testers found multiple bugs that could jeopardize the commitment date, they should be recorded in the Issue Log first to track, manage, and resolve them.
Topics