During the testing process, testers have found multiple bugs that could jeopardize the project commitment date. Which of the following tools should the project manager use first to update the findings

The correct answer is C. Issue log. An Issue Log is used to document any problems or issues that arise during the project execution phase, including bugs, that could affect the project's objectives such as deadlines. Since the testers found multiple bugs that could jeopardize the commitment date, they should be rec

Tools and documentation

Question

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date. Which of the following tools should the project manager use first to update the findings?

Options

  • ADefect log
  • BChange log
  • CIssue log
  • DRisk log

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    16% (4)
  • C
    76% (19)
  • D
    4% (1)

Explanation

An Issue Log is used to document any problems or issues that arise during the project execution phase, including bugs, that could affect the project's objectives such as deadlines. Since the testers found multiple bugs that could jeopardize the commitment date, they should be recorded in the Issue Log first to track, manage, and resolve them.

Topics

#Project Management Tools#Issue Management#Project Logs#Project Control