As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their…
The correct answer is B. Constructing an Ishikawa diagram to determine the root cause. The project team is likely constructing an Ishikawa diagram (also known as a Fishbone diagram) to identify the root cause of the poor quality of the project documentation. The Ishikawa diagram helps visually organize potential causes of an issue in categories, which allows the…
Question
As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?
Options
- AExecuting the approved contingency plan
- BConstructing an Ishikawa diagram to determine the root cause
- CUsing a Pareto chart to prioritize the different causes
- DEngaging the senior management team in regard to the issue
How the community answered
(16 responses)- A13% (2)
- B75% (12)
- C6% (1)
- D6% (1)
Explanation
The project team is likely constructing an Ishikawa diagram (also known as a Fishbone diagram) to identify the root cause of the poor quality of the project documentation. The Ishikawa diagram helps visually organize potential causes of an issue in categories, which allows the team to explore various factors that may have contributed to the problem, such as people, processes, tools, and materials.