PK0-005 · Question #202
A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?
The correct answer is A. Milestone. A milestone chart is the best chart to use to show major accomplishments for key events, because it displays the important deliverables or outcomes of a project along a timeline. A milestone chart can provide a high-level overview of the project progress and achievements…
Question
A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?
Options
- AMilestone
- BGantt
- CBurndown
- DPERT
How the community answered
(39 responses)- A77% (30)
- B8% (3)
- C3% (1)
- D13% (5)
Explanation
A milestone chart is the best chart to use to show major accomplishments for key events, because it displays the important deliverables or outcomes of a project along a timeline. A milestone chart can provide a high-level overview of the project progress and achievements, without showing the details of each task or activity. A milestone chart can also help communicate the project status and expectations to the stakeholders, and identify any potential risks or delays that may affect the project completion.