PK0-005 · Question #166
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the
The correct answer is C. the preferred reported communication channel.. This answer is based on the best practice of stakeholder management, which is to identify and document the communication preferences of each stakeholder or stakeholder group. The project manager should update the stakeholder register with the information gathered from the stakeho
Question
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:
Options
- Athe preferred sponsor's communication channel.
- Bthe preferred project manager's communication channel.
- Cthe preferred reported communication channel.
- Demail communication as the preferred communication channel.
How the community answered
(53 responses)- A9% (5)
- B4% (2)
- C85% (45)
- D2% (1)
Explanation
This answer is based on the best practice of stakeholder management, which is to identify and document the communication preferences of each stakeholder or stakeholder group. The project manager should update the stakeholder register with the information gathered from the stakeholder analysis, which includes the preferred communication channel for each stakeholder. The preferred reported communication channel reflects the majority preference of the stakeholders, as well as the minority preference of the face-to-face communicators. The project manager should use this information to plan and execute effective communication throughout the project life cycle.