PK0-005 · Question #138
A project manager reviews the watch list and notices the probability of occurrence has increased for one item listed in this document; consequently, frequent monitoring is required. Which of the…
The correct answer is D. Risk register. When a potential threat's probability increases and requires closer attention, it indicates a change in its risk status.
Question
A project manager reviews the watch list and notices the probability of occurrence has increased for one item listed in this document; consequently, frequent monitoring is required. Which of the following tools should the project manager update NEXT?
Options
- ADefect log
- BStakeholder register
- CIssue log
- DRisk register
How the community answered
(43 responses)- A16% (7)
- B9% (4)
- C2% (1)
- D72% (31)
Why each option
When a potential threat's probability increases and requires closer attention, it indicates a change in its risk status.
A defect log tracks identified flaws or bugs in deliverables, not changes in the probability of future uncertainties.
A stakeholder register lists project stakeholders and their attributes, not project risks.
An issue log tracks actual problems or challenges that have already occurred and require resolution, not potential future events whose probability has changed.
A watch list is used for low-priority risks that are monitored but not actively managed. If the probability of occurrence increases, the item is no longer merely 'watched' but becomes a more significant risk that needs formal recording and monitoring, thus requiring an update to the risk register. The risk register details identified risks, their probability, impact, and planned responses.
Concept tested: Project risk management tools
Topics
Community Discussion