PK0-004 · Question #985
A project manager reviewed a project's financials and determined the following: - The project has a burn rate of $15,000 per month. - The project has $70,000 left in its budget. - The project team…
The correct answer is C. Issue a change control request for additional funds to complete the project. The math reveals a clear funding deficit: 6 months × $15,000 = $90,000 needed, but only $70,000 remains - a $20,000 shortfall. Since the project will definitively run out of money before completion, the FIRST action is to issue a change control request for additional funds (C)…
Question
A project manager reviewed a project's financials and determined the following:
- The project has a burn rate of $15,000 per month.
- The project has $70,000 left in its budget.
- The project team needs six months to complete the remaining work.
Based on the information above, which of the following should the project manager perform FIRST?
Options
- AUpdate the risk register to show funding will run out prior to completion.
- BAttempt to crash the project schedule to reduce the time to complete.
- CIssue a change control request for additional funds to complete the project.
- DPrepare a budget analysis identifying the root cause of the overburn.
How the community answered
(51 responses)- A10% (5)
- B22% (11)
- C63% (32)
- D6% (3)
Explanation
The math reveals a clear funding deficit: 6 months × $15,000 = $90,000 needed, but only $70,000 remains - a $20,000 shortfall. Since the project will definitively run out of money before completion, the FIRST action is to issue a change control request for additional funds (C). This is the formal mechanism to surface the budget gap to decision-makers and get authorization to continue. Updating the risk register (A) is inappropriate here because this is no longer a risk (uncertain future event) - it is an active issue with a known outcome. Crashing the schedule (B) might reduce cost but requires authorization and analysis first. Preparing a root-cause budget analysis (D) is useful supporting material but is secondary to formally requesting the funds needed to keep the project alive.
Topics
Community Discussion
No community discussion yet for this question.