nerdexam
ExamsPK0-004Questions#985
CompTIA

PK0-004 · Question #985

PK0-004 Question #985: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-004 to reveal the answer and full explanation for question #985. The question stem and answer options stay visible for context.

Question

A project manager reviewed a project's financials and determined the following: - The project has a burn rate of $15,000 per month. - The project has $70,000 left in its budget. - The project team needs six months to complete the remaining work. Based on the information above, which of the following should the project manager perform FIRST?

Options

  • AUpdate the risk register to show funding will run out prior to completion.
  • BAttempt to crash the project schedule to reduce the time to complete.
  • CIssue a change control request for additional funds to complete the project.
  • DPrepare a budget analysis identifying the root cause of the overburn.

Unlock PK0-004 to see the answer

You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PK0-004 Practice