PK0-004 · Question #957
Which of the following represents the total efforts?
The correct answer is C. Project. A project represents the total, bounded efforts required to produce a specific outcome - it has a defined start, a defined end, and a complete scope of work that constitutes its 'total effort.' A program (A) is a group of related projects managed together. A portfolio (B) is a…
Question
Which of the following represents the total efforts?
Options
- AProgram
- BPortfolio
- CProject
- DOperations
How the community answered
(36 responses)- A6% (2)
- B3% (1)
- C89% (32)
- D3% (1)
Explanation
A project represents the total, bounded efforts required to produce a specific outcome - it has a defined start, a defined end, and a complete scope of work that constitutes its 'total effort.' A program (A) is a group of related projects managed together. A portfolio (B) is a collection of programs and projects aligned to strategic objectives - it is broader than a single total effort. Operations (D) are ongoing, repetitive business activities with no defined end, the opposite of a project's bounded total effort.
Topics
Community Discussion
No community discussion yet for this question.