PK0-004 · Question #957

PK0-004 Question #957: Real Exam Question with Answer & Explanation

The correct answer is C: Project. A project represents the total, bounded efforts required to produce a specific outcome - it has a defined start, a defined end, and a complete scope of work that constitutes its 'total effort.' A program (A) is a group of related projects managed together. A portfolio (B) is a co

Question

Which of the following represents the total efforts?

Options

  • AProgram
  • BPortfolio
  • CProject
  • DOperations

Explanation

A project represents the total, bounded efforts required to produce a specific outcome - it has a defined start, a defined end, and a complete scope of work that constitutes its 'total effort.' A program (A) is a group of related projects managed together. A portfolio (B) is a collection of programs and projects aligned to strategic objectives - it is broader than a single total effort. Operations (D) are ongoing, repetitive business activities with no defined end, the opposite of a project's bounded total effort.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice