PK0-004 · Question #834
A project manager presented the project risk plan to the project sponsor, and the project sponsor decided to cancel the project. Which of the following is the MOST likely reason for canceling the…
The correct answer is C. Unacceptable overall level of risks. When a project sponsor reviews the risk plan and finds the cumulative risk exposure exceeds the organization's tolerance, canceling the project is a rational business decision.
Question
A project manager presented the project risk plan to the project sponsor, and the project sponsor decided to cancel the project. Which of the following is the MOST likely reason for canceling the project?
Options
- AIncomplete risk plan
- BNo defined risk-related responsibilities
- CUnacceptable overall level of risks
- DToo many risks on the plan
How the community answered
(40 responses)- A8% (3)
- B3% (1)
- C80% (32)
- D10% (4)
Why each option
When a project sponsor reviews the risk plan and finds the cumulative risk exposure exceeds the organization's tolerance, canceling the project is a rational business decision.
An incomplete risk plan would prompt the sponsor to request completion before making a decision, not to cancel the project outright.
Undefined risk responsibilities represent a governance gap that would require assignment and correction, not a basis for project cancellation.
The sponsor evaluated the overall risk profile and determined it was beyond the organization's acceptable risk threshold or risk appetite. When the aggregate severity and likelihood of risks outweigh the expected business value, the sponsor - as the decision-making authority - is justified in canceling the project. This reflects a fundamental principle of risk governance: proceed only when risks are acceptable.
The quantity of risks alone is not a valid cancellation reason - it is the severity, probability, and acceptability of risks that matter, not their count.
Concept tested: Project risk tolerance and sponsor decision authority
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.