PK0-004 · Question #827

At the midway point of execution, the project plan calls for a full review of the risk register. To which of the following is the appropriate party to communicate the official results of this review?

The correct answer is D. Steering committee. A steering committee is a governing body of key stakeholders tasked with overseeing and supporting a project to ensure the attainment of its goals.

Project management concepts

Question

At the midway point of execution, the project plan calls for a full review of the risk register. To which of the following is the appropriate party to communicate the official results of this review?

Options

  • AAll stakeholders
  • BExecutive decision team
  • CFull project team
  • DSteering committee

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    10% (4)
  • D
    83% (33)

Explanation

A steering committee is a governing body of key stakeholders tasked with overseeing and supporting a project to ensure the attainment of its goals.

Topics

#risk register#steering committee#stakeholder communication#risk governance