PK0-004 · Question #827
At the midway point of execution, the project plan calls for a full review of the risk register. To which of the following is the appropriate party to communicate the official results of this review?
The correct answer is D. Steering committee. A steering committee is a governing body of key stakeholders tasked with overseeing and supporting a project to ensure the attainment of its goals.
Project management concepts
Question
At the midway point of execution, the project plan calls for a full review of the risk register. To which of the following is the appropriate party to communicate the official results of this review?
Options
- AAll stakeholders
- BExecutive decision team
- CFull project team
- DSteering committee
How the community answered
(40 responses)- A5% (2)
- B3% (1)
- C10% (4)
- D83% (33)
Explanation
A steering committee is a governing body of key stakeholders tasked with overseeing and supporting a project to ensure the attainment of its goals.
Topics
#risk register#steering committee#stakeholder communication#risk governance