During an active project, a meeting is set up to explain new internal processes. Which of the following MOST likely triggered this meeting?

The correct answer is D. The PMO standard requirements changed. A meeting to explain new internal processes is most directly triggered by a change in PMO standard requirements, as the PMO owns and enforces internal process standards.

Project management concepts

Question

During an active project, a meeting is set up to explain new internal processes. Which of the following MOST likely triggered this meeting?

Options

  • AThe scope of the project changed.
  • BThe sponsor requested additional functionality.
  • CA project team member left the organization.
  • DThe PMO standard requirements changed.

How the community answered

(50 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    2% (1)
  • D
    92% (46)

Why each option

A meeting to explain new internal processes is most directly triggered by a change in PMO standard requirements, as the PMO owns and enforces internal process standards.

AThe scope of the project changed.

A scope change would trigger a change control process and a scope review or change board meeting, not a meeting about new internal processes.

BThe sponsor requested additional functionality.

A sponsor requesting additional functionality would initiate a scope change request and review, not an internal process training session.

CA project team member left the organization.

A team member leaving would prompt resource reassignment and onboarding activities, not a meeting about new internal process standards.

DThe PMO standard requirements changed.Correct

The PMO is the organizational body responsible for defining, maintaining, and communicating internal project management standards and processes. When PMO requirements change, all affected project teams must be briefed to ensure compliance with the new standards. A meeting specifically focused on new internal processes is the expected communication mechanism when the PMO updates its requirements.

Concept tested: PMO role in setting and communicating internal process standards

Source: https://www.pmi.org/learning/library/project-management-office-value-7634

Topics

#PMO standards#internal processes#change triggers#process governance