nerdexam
CompTIA

PK0-004 · Question #717

To maintain an active project's progress, the project manager does not acknowledge any opposing input that was provided. Which of the following techniques is this an example of?

The correct answer is C. Forcing. Forcing (also called directing) is a conflict-resolution technique where one party pushes their position through without acknowledging or considering opposing views. The project manager is essentially overriding dissent to keep the project moving - a classic example of forcing…

Project management concepts

Question

To maintain an active project’s progress, the project manager does not acknowledge any opposing input that was provided. Which of the following techniques is this an example of?

Options

  • AMitigating
  • BNegotiating
  • CForcing
  • DAvoiding
  • EAccepting

How the community answered

(39 responses)
  • A
    3% (1)
  • C
    92% (36)
  • E
    5% (2)

Explanation

Forcing (also called directing) is a conflict-resolution technique where one party pushes their position through without acknowledging or considering opposing views. The project manager is essentially overriding dissent to keep the project moving - a classic example of forcing. Avoiding means withdrawing from the conflict entirely. Mitigating reduces the impact of a risk or conflict. Accepting means acknowledging the conflict but taking no action. Negotiating involves give-and-take from both sides.

Topics

#conflict resolution#forcing technique#stakeholder input#project control

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice