PK0-004 · Question #715
A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This…
The correct answer is B. Ask the functional manager to provide a resource with the same level of allocation. In a functional organization, the project manager lacks direct authority over resources and must work through the functional manager to resolve allocation conflicts.
Question
A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date. Which of the following should the project manager do NEXT?
Options
- AAsk the PMO to mitigate the risk related to insufficient resources
- BAsk the functional manager to provide a resource with the same level of allocation
- CRemove 20 of allocation of the resource from the secondary
- DAsk the resource to improve performance to target with commitment date.
How the community answered
(15 responses)- A13% (2)
- B73% (11)
- C7% (1)
- D7% (1)
Why each option
In a functional organization, the project manager lacks direct authority over resources and must work through the functional manager to resolve allocation conflicts.
Asking the PMO to mitigate risk does not directly resolve the resource conflict; the functional manager is the correct authority to address the allocation problem.
In a functional organizational structure, resources report to and are controlled by functional managers who determine their availability and assignments. When a resource's split allocation to a secondary project threatens the primary project's commitment date, the project manager must request that the functional manager supply a replacement resource with the full required allocation, as the project manager has no authority to unilaterally override the existing assignment.
The project manager does not have authority in a functional organization to remove a resource's allocation from a secondary project managed by a different functional area.
Asking the resource to improve performance does not change the structural reality that 20% allocation to a secondary project leaves insufficient availability, regardless of individual effort.
Concept tested: Resource management in functional organizational structures
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.