A functional manager pulled a resource from a current project to work on a higher-priority project but did not offer a backfill resource. Which of the following should the project manager do FIRST?
Options
- AReport the project as at risk and share the issue with the project team.
- BMeet with the functional manager to discuss the issue.
- CDelay the task in the schedule and inform the sponsor.
- DOpen a change request to reduce the project scope.