PK0-004 · Question #675

PK0-004 Question #675: Real Exam Question with Answer & Explanation

The correct answer is B: corporate strategy.. Programs and projects within a portfolio are not necessarily related to one another in a direct way. And projects may independently exist within the portfolio (in other words, the project isn’t related to a program but belongs to the portfolio). However, the overall objective of

Question

A project portfolio will MOST likely align to:

Options

  • Aconsumer demand.
  • Bcorporate strategy.
  • Clessons learned.
  • DPMO guidelines.

Explanation

Programs and projects within a portfolio are not necessarily related to one another in a direct way. And projects may independently exist within the portfolio (in other words, the project isn’t related to a program but belongs to the portfolio). However, the overall objective of any program or project in a portfolio is to meet the strategic objectives of the portfolio, which in turn should meet the strategic objectives of the business unit or corporation.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice