PK0-004 · Question #675
PK0-004 Question #675: Real Exam Question with Answer & Explanation
The correct answer is B: corporate strategy.. Programs and projects within a portfolio are not necessarily related to one another in a direct way. And projects may independently exist within the portfolio (in other words, the project isn’t related to a program but belongs to the portfolio). However, the overall objective of
Question
Options
- Aconsumer demand.
- Bcorporate strategy.
- Clessons learned.
- DPMO guidelines.
Explanation
Programs and projects within a portfolio are not necessarily related to one another in a direct way. And projects may independently exist within the portfolio (in other words, the project isn’t related to a program but belongs to the portfolio). However, the overall objective of any program or project in a portfolio is to meet the strategic objectives of the portfolio, which in turn should meet the strategic objectives of the business unit or corporation.
Community Discussion
No community discussion yet for this question.