nerdexam
CompTIA

PK0-004 · Question #631

Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below: Which of the following is MOST likely the cause?

The correct answer is D. Insufficient resources assigned. Task ID 3 has not started and has zero progress; the most direct operational cause is that no resources are assigned to perform the work.

Project management concepts

Question

Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below:

Which of the following is MOST likely the cause?

Exhibits

PK0-004 question #631 exhibit 1
PK0-004 question #631 exhibit 2
PK0-004 question #631 exhibit 3

Options

  • APredecessors not properly identified
  • BScope change
  • CRetrospective in progress
  • DInsufficient resources assigned

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    22% (4)
  • C
    6% (1)
  • D
    61% (11)

Why each option

Task ID 3 has not started and has zero progress; the most direct operational cause is that no resources are assigned to perform the work.

APredecessors not properly identified

Predecessors not properly identified would cause sequencing or dependency errors in the schedule, but would not by itself result in zero work if resources were present and available.

BScope change

A scope change alters deliverables or requirements but would trigger a formal change request process, not simply cause a task to silently fail to start.

CRetrospective in progress

A retrospective is an agile ceremony for reflecting on a completed sprint and would not block an individual scheduled task from initiating.

DInsufficient resources assignedCorrect

Insufficient resources assigned means no team members or equipment are available to execute the task, directly preventing it from starting on schedule. Without the necessary people or materials assigned, the task remains idle regardless of its scheduled start date. This is the most immediate and concrete reason a task would show zero progress with no start.

Concept tested: Resource assignment impact on task scheduling

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#schedule analysis#resource management#schedule delays#task scheduling

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice