Which of the following characteristics would stakeholders MOST likely have?

The correct answer is A. Provide input, vested interest, affected by project. https://opentextbc.ca/projectmanagement/chapter/chapter-5-project-stakeholders-project-

Project management concepts

Question

Which of the following characteristics would stakeholders MOST likely have?

Options

  • AProvide input, vested interest, affected by project
  • BNo vested interest, funding control, expertise
  • CProject steering, funding control, vested interest
  • DExpertise, provide input, good at controlling

How the community answered

(24 responses)
  • A
    92% (22)
  • C
    4% (1)
  • D
    4% (1)

Explanation

https://opentextbc.ca/projectmanagement/chapter/chapter-5-project-stakeholders-project-