PK0-004 · Question #573
PK0-004 Question #573: Real Exam Question with Answer & Explanation
The correct answer is B: Project A can be crashed using Project B's resources.. The dependency is the bottleneck - Project B cannot fully proceed until Project A finishes. The fastest legitimate solution is to crash Project A by reallocating Project B's resources to accelerate it. This shortens Project A's duration so both projects can proceed properly. Opti
Question
Options
- AProject A can reduce the number of deliverables.
- BProject A can be crashed using Project B's resources.
- CProject B can have its resources leveled.
- DProject B can begin without Project A completing, therefore accepting future rework.
Explanation
The dependency is the bottleneck - Project B cannot fully proceed until Project A finishes. The fastest legitimate solution is to crash Project A by reallocating Project B's resources to accelerate it. This shortens Project A's duration so both projects can proceed properly. Option D (accepting future rework) introduces known quality risk. Resource leveling (C) only addresses resource conflicts, not the dependency issue. Reducing deliverables (A) changes scope without solving the scheduling problem.
Community Discussion
No community discussion yet for this question.