nerdexam
ExamsPK0-004Questions#573
CompTIA

PK0-004 · Question #573

PK0-004 Question #573: Real Exam Question with Answer & Explanation

The correct answer is B: Project A can be crashed using Project B's resources.. The dependency is the bottleneck - Project B cannot fully proceed until Project A finishes. The fastest legitimate solution is to crash Project A by reallocating Project B's resources to accelerate it. This shortens Project A's duration so both projects can proceed properly. Opti

Question

Project B cannot start before Project A is complete, but Project B has been given authorization to begin to meet legislative requirements. Which of the following is the BEST way to expedite the projects?

Options

  • AProject A can reduce the number of deliverables.
  • BProject A can be crashed using Project B's resources.
  • CProject B can have its resources leveled.
  • DProject B can begin without Project A completing, therefore accepting future rework.

Explanation

The dependency is the bottleneck - Project B cannot fully proceed until Project A finishes. The fastest legitimate solution is to crash Project A by reallocating Project B's resources to accelerate it. This shortens Project A's duration so both projects can proceed properly. Option D (accepting future rework) introduces known quality risk. Resource leveling (C) only addresses resource conflicts, not the dependency issue. Reducing deliverables (A) changes scope without solving the scheduling problem.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice