Project B cannot start before Project A is complete, but Project B has been given authorization to begin to meet legislative requirements. Which of the following is the BEST way to expedite the…

The correct answer is B. Project A can be crashed using Project B's resources. The dependency is the bottleneck - Project B cannot fully proceed until Project A finishes. The fastest legitimate solution is to crash Project A by reallocating Project B's resources to accelerate it. This shortens Project A's duration so both projects can proceed properly…

Project management concepts

Question

Project B cannot start before Project A is complete, but Project B has been given authorization to begin to meet legislative requirements. Which of the following is the BEST way to expedite the projects?

Options

  • AProject A can reduce the number of deliverables.
  • BProject A can be crashed using Project B's resources.
  • CProject B can have its resources leveled.
  • DProject B can begin without Project A completing, therefore accepting future rework.

How the community answered

(35 responses)
  • A
    23% (8)
  • B
    63% (22)
  • C
    6% (2)
  • D
    9% (3)

Explanation

The dependency is the bottleneck - Project B cannot fully proceed until Project A finishes. The fastest legitimate solution is to crash Project A by reallocating Project B's resources to accelerate it. This shortens Project A's duration so both projects can proceed properly. Option D (accepting future rework) introduces known quality risk. Resource leveling (C) only addresses resource conflicts, not the dependency issue. Reducing deliverables (A) changes scope without solving the scheduling problem.

Topics

#schedule crashing#project dependencies#resource sharing#schedule compression

Community Discussion

No community discussion yet for this question.