PK0-004 · Question #549
An audit, project change, task initiation/completion, gate review, and incident response are examples of:
The correct answer is D. communication triggers. Communication triggers are specific events or conditions that initiate or require a communication action within a project. Audits, project changes, task initiation/completion, gate reviews, and incident responses are all defined triggers that signal stakeholders must be…
Question
An audit, project change, task initiation/completion, gate review, and incident response are examples of:
Options
- Achange control.
- Bstatus reporting.
- Crisk events.
- Dcommunication triggers.
How the community answered
(37 responses)- B3% (1)
- C5% (2)
- D92% (34)
Explanation
Communication triggers are specific events or conditions that initiate or require a communication action within a project. Audits, project changes, task initiation/completion, gate reviews, and incident responses are all defined triggers that signal stakeholders must be informed. They are not change control procedures (A), which govern how changes are managed. They are not status reports (B), which are scheduled updates. And they are not risk events (C), which relate to uncertainty and potential threats. Communication triggers are the 'when' of project communications.
Topics