PK0-004 · Question #538

PK0-004 Question #538: Real Exam Question with Answer & Explanation

Sign in or unlock PK0-004 to reveal the answer and full explanation for question #538. The question stem and answer options stay visible for context.

Question

A project sponsor informs the project manager that the project completion date must be moved one month earlier. Which of the following should the project manager do NEXT?

Options

  • ARecalculate the critical path, determine the new cost, schedule baselines, and initiate the change
  • BRecalculate the schedule and cost variance, and report the changes to the project stakeholders
  • CCalculate the cost of crashing the schedule, and obtain the stakeholders' approval for the new
  • DCalculate the additional resource requirements that are necessary to meet the new project