CompTIA
PK0-004 · Question #538
PK0-004 Question #538: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-004 to reveal the answer and full explanation for question #538. The question stem and answer options stay visible for context.
Question
A project sponsor informs the project manager that the project completion date must be moved one month earlier. Which of the following should the project manager do NEXT?
Options
- ARecalculate the critical path, determine the new cost, schedule baselines, and initiate the change
- BRecalculate the schedule and cost variance, and report the changes to the project stakeholders
- CCalculate the cost of crashing the schedule, and obtain the stakeholders' approval for the new
- DCalculate the additional resource requirements that are necessary to meet the new project
Unlock PK0-004 to see the answer
You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.