PK0-004 · Question #530

A company has completed its annual strategic planning session. As a result, several related projects, which will achieve the company's technological improvement goals, are identified. Which of the…

The correct answer is B. Program. A Program is a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually. The key indicator here is 'several related projects' with a shared goal (technological improvement). A Portfolio (A) is a broader…

Project management concepts

Question

A company has completed its annual strategic planning session. As a result, several related projects, which will achieve the company's technological improvement goals, are identified. Which of the following BEST describes these projects?

Options

  • APortfolio
  • BProgram
  • CDeliverable
  • DOutcome

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    89% (34)
  • C
    8% (3)

Explanation

A Program is a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually. The key indicator here is 'several related projects' with a shared goal (technological improvement). A Portfolio (A) is a broader collection of programs, projects, and operations aligned to strategic goals - not necessarily related to each other. A Deliverable (C) is a specific output, not a grouping of projects. An Outcome (D) is the result or benefit achieved, not the projects themselves.

Topics

#program management#portfolio#project hierarchy#strategic alignment