An approved change was implemented. Which of the following should be accomplished NEXT?

The correct answer is B. Validate the change. Identify and document - Evaluate impact and justification - Regression plan (Reverse changes) - Identify approval authority - Obtain approval - Implement change - Validate change/quality check - Update documents/audit documents/version control - Communicate throughout as needed

Project management concepts

Question

An approved change was implemented. Which of the following should be accomplished NEXT?

Options

  • AUpdate the documentation.
  • BValidate the change.
  • CUpdate the project sponsor.
  • DValidate the impact.

How the community answered

(58 responses)
  • A
    2% (1)
  • B
    86% (50)
  • C
    3% (2)
  • D
    9% (5)

Explanation

  • Identify and document - Evaluate impact and justification - Regression plan (Reverse changes) - Identify approval authority - Obtain approval - Implement change - Validate change/quality check - Update documents/audit documents/version control - Communicate throughout as needed

Topics

#change control#change validation#change management process