PK0-004 · Question #528
An approved change was implemented. Which of the following should be accomplished NEXT?
The correct answer is B. Validate the change. Identify and document - Evaluate impact and justification - Regression plan (Reverse changes) - Identify approval authority - Obtain approval - Implement change - Validate change/quality check - Update documents/audit documents/version control - Communicate throughout as needed
Project management concepts
Question
An approved change was implemented. Which of the following should be accomplished NEXT?
Options
- AUpdate the documentation.
- BValidate the change.
- CUpdate the project sponsor.
- DValidate the impact.
How the community answered
(58 responses)- A2% (1)
- B86% (50)
- C3% (2)
- D9% (5)
Explanation
- Identify and document - Evaluate impact and justification - Regression plan (Reverse changes) - Identify approval authority - Obtain approval - Implement change - Validate change/quality check - Update documents/audit documents/version control - Communicate throughout as needed
Topics
#change control#change validation#change management process