PK0-004 · Question #526
A company recently went through a project requiring new equipment, new software, and retraining of personnel. This is MOST likely a result of:
The correct answer is A. an internal reorganization. Acquiring new equipment, deploying new software, and retraining staff are hallmarks of an internal reorganization - a broad, structural change within the company that alters how the organization operates. Internal reorganizations often require new tools and updated workforce…
Question
A company recently went through a project requiring new equipment, new software, and retraining of personnel. This is MOST likely a result of:
Options
- Aan internal reorganization.
- Boutsourcing.
- Ca business process change.
- Dresource allocation.
How the community answered
(30 responses)- A93% (28)
- C3% (1)
- D3% (1)
Explanation
Acquiring new equipment, deploying new software, and retraining staff are hallmarks of an internal reorganization - a broad, structural change within the company that alters how the organization operates. Internal reorganizations often require new tools and updated workforce skills to align with the new operating model. Outsourcing (B) would involve transferring work to external parties, not internal equipment/software upgrades. A business process change (C) typically targets a specific workflow, whereas the combination of all three elements (equipment, software, retraining) implies a broader organizational transformation. Resource allocation (D) is simply assigning existing people to tasks and would not require equipment purchases or retraining.
Topics
Community Discussion
No community discussion yet for this question.