nerdexam
CompTIA

PK0-004 · Question #518

When developing a project schedule, which of the following resources is the BEST to estimate task duration?

The correct answer is C. Project team. The project team comprises the project manager, the project management team, and other individual team members. The individual team members perform project work and may not be involved in the management side of the project. The project team contains people from different groups…

Project management concepts

Question

When developing a project schedule, which of the following resources is the BEST to estimate task duration?

Options

  • AProject manager
  • BProject scheduler
  • CProject team
  • DProject sponsor

How the community answered

(40 responses)
  • A
    3% (1)
  • C
    93% (37)
  • D
    5% (2)

Explanation

The project team comprises the project manager, the project management team, and other individual team members. The individual team members perform project work and may not be involved in the management side of the project. The project team contains people from different groups who possess knowledge on specific subjects or have unique skill sets to carry out project work. The project team's duties include: - Use expertise to contribute to completing project tasks. - Contribute deliverables on schedule. - Provide estimates of task duration. - Provide estimates of costs and dependencies.

Topics

#task duration estimation#project team#scheduling#estimation techniques

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice