Question

A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager do NEXT?

Options

  • AAsk the resource manager to deallocate the resource from the second project.
  • BAsk the resource manager to assign a new resource with 40% of allocation.
  • CKeep the resource 100% allocated in the project, as per the initial plan.
  • DChange the resource to 60% of allocation and review the mitigation plan.