PK0-004 · Question #504
A new executive has joined the organization and is considering adding deliverables to the scope. The sponsor agrees with the executive but does not want to change the completion date. Which of the…
The correct answer is A. Fast-track some tasks to free up time. D. Request additional funds to get more resources. Accommodating additional scope without extending the completion date only means that you should speed things up (fast-tracking) to make room for executing the activities to cover the additional scope. Also, additional resources (budget) is very logical to compensate for the…
Question
A new executive has joined the organization and is considering adding deliverables to the scope. The sponsor agrees with the executive but does not want to change the completion date. Which of the following options would be MOST useful to the project manager to accommodate the new scope without extending the completion date? (Choose two.)
Options
- AFast-track some tasks to free up time.
- BRemove some of the previous deliverables.
- CDocument the impact to the scope.
- DRequest additional funds to get more resources.
- EDeny the scope change.
- FPerform regression analysis on the changes.
How the community answered
(53 responses)- A51% (27)
- B13% (7)
- C26% (14)
- E4% (2)
- F6% (3)
Explanation
Accommodating additional scope without extending the completion date only means that you should speed things up (fast-tracking) to make room for executing the activities to cover the additional scope. Also, additional resources (budget) is very logical to compensate for the additional work.
Topics