PK0-004 · Question #500
Which of the following is the BEST indicator of project failure?
The correct answer is D. Several changes being made to the project. Several changes being made to a project is the strongest indicator of potential failure. Excessive change requests signal poor initial planning, unstable requirements, scope creep, and loss of control over the project baseline-all of which are leading causes of project failure…
Question
Which of the following is the BEST indicator of project failure?
Options
- AProduct deficiencies revealed during the monitor and control phase
- BProject team members disagreeing on milestones
- CProject deliverables completed behind schedule
- DSeveral changes being made to the project
How the community answered
(35 responses)- A11% (4)
- B3% (1)
- C6% (2)
- D80% (28)
Explanation
Several changes being made to a project is the strongest indicator of potential failure. Excessive change requests signal poor initial planning, unstable requirements, scope creep, and loss of control over the project baseline-all of which are leading causes of project failure. Product deficiencies found during monitor/control are expected and manageable. Team disagreements on milestones are a communication/alignment issue that can be resolved. Schedule delays are a symptom that can sometimes be recovered. However, a high volume of changes indicates fundamental instability in the project's foundation, which is the most reliable predictor of overall project failure.