PK0-004 · Question #480
Which of the following project roles is ultimately responsible for all project artifacts?
The correct answer is C. Project manager. The project manager is ultimately responsible for all project artifacts-documents, plans, deliverables, reports, and other outputs produced throughout the project lifecycle. This includes the project charter, schedule, risk register, status reports, and final deliverables…
Question
Which of the following project roles is ultimately responsible for all project artifacts?
Options
- AProject sponsor
- BProject coordinator
- CProject manager
- DProject team
How the community answered
(43 responses)- A5% (2)
- B2% (1)
- C93% (40)
Explanation
The project manager is ultimately responsible for all project artifacts-documents, plans, deliverables, reports, and other outputs produced throughout the project lifecycle. This includes the project charter, schedule, risk register, status reports, and final deliverables. While the project sponsor (A) provides funding and high-level authority, they are not accountable for artifacts. The project coordinator (B) assists with administrative tasks. The project team (D) creates many artifacts but accountability rolls up to the project manager, who owns them on behalf of the project.
Topics