nerdexam
ExamsPK0-004Questions#457
CompTIA

PK0-004 · Question #457

PK0-004 Question #457: Real Exam Question with Answer & Explanation

The correct answer is A: document the change. Change management best practice requires that all change requests be formally documented before any other action is taken. Documentation creates an official record that captures the nature, justification, scope impact, schedule impact, and cost impact of the change-forming the ba

Question

A project sponsor approaches the project manager with a change request. During the conversation, the project sponsor claims to understand the impact of the change to the project length and has the budget to handle the cost. The sponsor also tells the project manager to send whatever needs a signature. The project manager's NEXT step should be to:

Options

  • Adocument the change
  • Bimplement the change
  • Ccommunicate the change
  • Dprioritize the change

Explanation

Change management best practice requires that all change requests be formally documented before any other action is taken. Documentation creates an official record that captures the nature, justification, scope impact, schedule impact, and cost impact of the change-forming the basis for formal approval. The sponsor's verbal acknowledgment of impact and budget is insufficient on its own; without documented evidence, there is no audit trail or basis for proper evaluation and approval. Implementing, communicating, or prioritizing the change all come after the change has been formally documented and approved through the change control process.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice