In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:

The correct answer is D. a benched resource pool. Benched resources - they're free and ready to be assigned for use.

Project management concepts

Question

In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:

Options

  • Aa dedicated resource pool
  • Ban allocated resource pool
  • Ca shared resource pool
  • Da benched resource pool

How the community answered

(45 responses)
  • A
    7% (3)
  • B
    4% (2)
  • C
    13% (6)
  • D
    76% (34)

Explanation

Benched resources - they're free and ready to be assigned for use.

Topics

#projectized organization#resource pool#benched resources#resource management