In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:
The correct answer is D. a benched resource pool. Benched resources - they're free and ready to be assigned for use.
Project management concepts
Question
In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:
Options
- Aa dedicated resource pool
- Ban allocated resource pool
- Ca shared resource pool
- Da benched resource pool
How the community answered
(45 responses)- A7% (3)
- B4% (2)
- C13% (6)
- D76% (34)
Explanation
Benched resources - they're free and ready to be assigned for use.