PK0-004 · Question #449

A project manager is assigned a project that is part of the company's strategic objectives. Of which of the following is the project a part?

The correct answer is B. Portfolio. A portfolio is a collection of projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic business objectives. When a project is directly aligned with or supports the organization's strategic goals, it belongs to a portfolio. A program is…

Project management concepts

Question

A project manager is assigned a project that is part of the company's strategic objectives. Of which of the following is the project a part?

Options

  • AProject management office
  • BPortfolio
  • CProgram
  • DMission statement

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    87% (26)
  • C
    3% (1)
  • D
    7% (2)

Explanation

A portfolio is a collection of projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic business objectives. When a project is directly aligned with or supports the organization's strategic goals, it belongs to a portfolio. A program is a group of related projects managed together for benefits not available individually, but it is not necessarily tied to strategic objectives in the same direct way. A PMO is an organizational structure, not a collection of work. A mission statement defines organizational purpose, not a grouping of projects.