A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation. Which of the following actions has the PM…
The correct answer is C. Evaluating the impact of the risk. It clearly states he submitted it for approval, the assumption is that he sent it to the CCB to be approved. What he failed to do was weigh the risks.
Project management concepts
Question
A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation. Which of the following actions has the PM omitted?
Options
- AIdentifying the risk
- BObtaining approval from the CCB
- CEvaluating the impact of the risk
- DCommunicating to stakeholders
How the community answered
(36 responses)- A3% (1)
- B8% (3)
- C83% (30)
- D6% (2)
Explanation
It clearly states he submitted it for approval, the assumption is that he sent it to the CCB to be approved. What he failed to do was weigh the risks.
Topics
#change management#impact assessment#change request process#CCB