CompTIA
PK0-004 · Question #436
A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following…
The correct answer is C. Review the communications plan to ensure proper involvement E. Ensure the functional manager is on the status report distribution list. If the project is already underway, updating the charter does nothing to address this issue.
Project management concepts
Question
A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)
Options
- AUpdate the project charter to include the functional manager as a key stakeholder
- BPublish the project schedule to the functional manager
- CReview the communications plan to ensure proper involvement
- DAdd the incident to the issue log and seek resolution
- EEnsure the functional manager is on the status report distribution list
How the community answered
(58 responses)- A7% (4)
- B14% (8)
- C76% (44)
- D3% (2)
Explanation
If the project is already underway, updating the charter does nothing to address this issue.
Topics
#communications plan#stakeholder distribution#functional manager#status reporting