PK0-004 · Question #421
In a Scrum retrospective, which of the following categories are used to classify the feedback from the team?
The correct answer is C. Pluses and minuses. In Scrum retrospectives, the classic feedback classification uses 'Pluses' (what went well and should continue) and 'Minuses' (what did not go well and should change or be improved). This plus/delta or plus/minus format is a standard retrospective technique that helps teams…
Question
In a Scrum retrospective, which of the following categories are used to classify the feedback from the team?
Options
- ADirect and indirect
- BPros and cons
- CPluses and minuses
- DLikes and dislikes
How the community answered
(36 responses)- A3% (1)
- C92% (33)
- D6% (2)
Explanation
In Scrum retrospectives, the classic feedback classification uses 'Pluses' (what went well and should continue) and 'Minuses' (what did not go well and should change or be improved). This plus/delta or plus/minus format is a standard retrospective technique that helps teams identify strengths to preserve and weaknesses to address. 'Pros and cons' (B) and 'likes and dislikes' (D) are similar in feel but are not the standard Scrum terminology. 'Direct and indirect' (A) is not a retrospective categorization at all.