PK0-004 · Question #416

A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and requested a project manager to work with the firm. The PMO declines to assign a…

The correct answer is C. This is ongoing work the vendor has been hired to perform. Its mentioned in the question itself that it is going to be ongoing work, but a project is a temporary endeavor, so a project manager shouldn't be needed in this situation

Basics of IT and governance

Question

A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and requested a project manager to work with the firm. The PMO declines to assign a project manager and refers to another department within the company. Which of the following is MOST likely the reason for this?

Options

  • AThere are not enough project managers available for additional work
  • BThe work does not align with the strategic objectives of the organization
  • CThis is ongoing work the vendor has been hired to perform
  • DThe third party has a reputation for expertise in this area

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    76% (19)
  • D
    8% (2)

Explanation

Its mentioned in the question itself that it is going to be ongoing work, but a project is a temporary endeavor, so a project manager shouldn't be needed in this situation

Topics

#PMO governance#ongoing operations#project vs operations#organizational structure