PK0-004 · Question #407

A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well. Which of the following stages BEST explains this…

The correct answer is D. Storming. Storming: Team members begin to assert themselves and control issues that emerge. Personality differences begin to arise. Conflicts result because team members differ in the way they want to do the project work or in the way they want to make decisions.

Project management concepts

Question

A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well. Which of the following stages BEST explains this situation?

Options

  • ANorming
  • BPerforming
  • CForming
  • DStorming

How the community answered

(30 responses)
  • A
    3% (1)
  • C
    3% (1)
  • D
    93% (28)

Explanation

Storming: Team members begin to assert themselves and control issues that emerge. Personality differences begin to arise. Conflicts result because team members differ in the way they want to do the project work or in the way they want to make decisions.

Topics

#Tuckman stages#team development#storming#conflict management