PK0-004 · Question #254
In the scope statement it is mentioned there is a strong possibility of a hurricane impacting the schedule at any given time. This notation would be considered a(n):
The correct answer is D. Risk. A risk is an uncertain future event that could positively or negatively affect project objectives; noting hurricane probability in the scope statement is a classic example of identifying a schedule risk.
Question
In the scope statement it is mentioned there is a strong possibility of a hurricane impacting the schedule at any given time. This notation would be considered a(n):
Options
- AAssumption
- BIssue
- CConstraint
- DRisk
How the community answered
(33 responses)- A3% (1)
- B3% (1)
- C9% (3)
- D85% (28)
Why each option
A risk is an uncertain future event that could positively or negatively affect project objectives; noting hurricane probability in the scope statement is a classic example of identifying a schedule risk.
An assumption is a factor believed to be true for planning purposes without proof, not a potentially harmful future event with acknowledged uncertainty.
An issue is a problem or concern that has already occurred and requires immediate action, whereas a hurricane in this context is only a possibility.
A constraint is a limiting factor already imposed on the project (such as a fixed deadline or budget cap), not a future uncertain event.
A risk is defined as an uncertain event or condition that, if it occurs, has an effect on project objectives such as schedule, cost, or scope. A hurricane is a potential future event with an uncertain probability of occurrence that could delay the schedule, making it a risk by definition.
Concept tested: Distinguishing risks from assumptions, issues, and constraints
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok