PK0-004 · Question #22

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which…

The correct answer is C. Implement change control management. Informal hallway meetings are bypassing the formal change process, causing unauthorized scope additions that have pushed the project behind schedule. Implementing change control management is the corrective action that stops this at the source.

Project management concepts

Question

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?

Options

  • AUpdate the scope management plan.
  • BModify the project baselines.
  • CImplement change control management.
  • DInform the stakeholders of the issue.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    86% (24)
  • D
    4% (1)

Why each option

Informal hallway meetings are bypassing the formal change process, causing unauthorized scope additions that have pushed the project behind schedule. Implementing change control management is the corrective action that stops this at the source.

AUpdate the scope management plan.

Updating the scope management plan defines how scope will be managed going forward but does not address the immediate problem of changes already being implemented without authorization.

BModify the project baselines.

Modifying project baselines is an outcome of formally approved changes, not a corrective action for uncontrolled scope additions that have already occurred.

CImplement change control management.Correct

Change control management establishes a formal, documented process for submitting, evaluating, approving, and tracking all changes to project scope. Without it, informal communications like hallway meetings result in untracked work that inflates scope without updating the schedule or budget. Enforcing this process ensures all future modifications are properly assessed and authorized before implementation.

DInform the stakeholders of the issue.

Informing stakeholders is a communication action that does not resolve the root cause, which is the absence of a formal change control process preventing unauthorized changes.

Concept tested: Implementing formal change control to prevent scope creep

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#change control#scope management#requirements management#stakeholder communication