A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:
The correct answer is B. key stakeholders. Key stakeholder are absolutely the ones you want to notify, they have skin in the game and what may be minor to the PM might not be for a stakeholder. Risk acceptance is different for everyone and everyone perceives risks differently.
Project management concepts
Question
A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:
Options
- Ainternal project team.
- Bkey stakeholders.
- Caffected team members.
- Dfull project team.
How the community answered
(26 responses)- A4% (1)
- B73% (19)
- C15% (4)
- D8% (2)
Explanation
Key stakeholder are absolutely the ones you want to notify, they have skin in the game and what may be minor to the PM might not be for a stakeholder. Risk acceptance is different for everyone and everyone perceives risks differently.