PK0-004 · Question #159

While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:

The correct answer is A. quality plan. Create a Quality Management Plan You now need to set standards and define parameters to assess project quality. Poor quality management is a major cause of project failure, and as a project manager it is your responsibility to ensure that your major deliverables are completed…

Project management concepts

Question

While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:

Options

  • Aquality plan.
  • Bproject management plan.
  • Crisk register.
  • Dprocess diagram.

How the community answered

(34 responses)
  • A
    91% (31)
  • B
    6% (2)
  • D
    3% (1)

Explanation

Create a Quality Management Plan You now need to set standards and define parameters to assess project quality. Poor quality management is a major cause of project failure, and as a project manager it is your responsibility to ensure that your major deliverables are completed with an acceptable level of quality.

Topics

#risk ranking#qualitative risk analysis#probability and impact#risk management plan