PK0-004 · Question #1065
A company has suffered major delays on key projects for new low-cost ink printers. Joe, a project manager, is meeting with the steering committee members to discuss some potential enhancements…
The correct answer is C. Obtaining approvals. Joe has already identified the potential enhancements (identifying) and is now presenting them to the steering committee - the decision-making body with authority to authorize changes. This step in the change process is 'obtaining approvals,' where the proposed changes are…
Question
A company has suffered major delays on key projects for new low-cost ink printers. Joe, a project manager, is meeting with the steering committee members to discuss some potential enhancements. Which of the following change processes is Joe performing?
Options
- AIdentifying approvers
- BDocumenting approvals
- CObtaining approvals
- DConducting quality approvals
How the community answered
(26 responses)- A8% (2)
- B4% (1)
- C88% (23)
Explanation
Joe has already identified the potential enhancements (identifying) and is now presenting them to the steering committee - the decision-making body with authority to authorize changes. This step in the change process is 'obtaining approvals,' where the proposed changes are presented to the appropriate stakeholders for a formal go/no-go decision. 'Identifying approvers' (A) would be the earlier step of determining who has authority to approve. 'Documenting approvals' (B) happens after the decision is made. 'Conducting quality approvals' (D) is not a standard change management step and does not fit this scenario.
Topics
Community Discussion
No community discussion yet for this question.