PK0-004 · Question #1063
PK0-004 Question #1063: Real Exam Question with Answer & Explanation
The correct answer is D: Work with the sponsor to determine existing requirements that can be removed.. Adding scope without adjusting cost or schedule violates the triple constraint - something must give. The most professional and constructive response is to negotiate with the sponsor: if the new requirement must be added and the budget and timeline are fixed, then something of eq
Question
Options
- AReject the additional requirement, as there is no time or budget allocated.
- BAccept the requirement and ask the project team to work faster.
- CAccept the requirement and add it to the risk register.
- DWork with the sponsor to determine existing requirements that can be removed.
Explanation
Adding scope without adjusting cost or schedule violates the triple constraint - something must give. The most professional and constructive response is to negotiate with the sponsor: if the new requirement must be added and the budget and timeline are fixed, then something of equal weight must be removed to make room. Rejecting the requirement outright (A) is unilateral and dismissive of the sponsor's authority. Accepting it and asking the team to work faster (B) is unrealistic and can harm morale and quality. Adding it to the risk register (C) doesn't resolve the constraint conflict - it just documents it. Option D respects the sponsor's goals while maintaining project integrity.