nerdexam
CompTIA

PK0-004 · Question #1042

The CCB places a production freeze during the month of February. A project has already been scheduled for activation on the last Saturday of February. Which of the following will MOST likely occur?

The correct answer is A. The project manager will be asked to move one week to accommodate the freeze. A Change Control Board (CCB) has organizational authority over production environments, and a production freeze means no deployments or activations are permitted during that period. The most practical and realistic outcome is that the CCB asks the project manager to reschedule…

Basics of IT and governance

Question

The CCB places a production freeze during the month of February. A project has already been scheduled for activation on the last Saturday of February. Which of the following will MOST likely occur?

Options

  • AThe project manager will be asked to move one week to accommodate the freeze.
  • BThe CCB will place the project on an indefinite hold.
  • CThe project team will work overtime to activate the project before the freeze.
  • DThe sponsor will ignore the systemwide freeze and proceed with the project.

How the community answered

(46 responses)
  • A
    83% (38)
  • B
    4% (2)
  • C
    2% (1)
  • D
    11% (5)

Explanation

A Change Control Board (CCB) has organizational authority over production environments, and a production freeze means no deployments or activations are permitted during that period. The most practical and realistic outcome is that the CCB asks the project manager to reschedule the activation by one week - moving it just outside the freeze window. Placing the project on indefinite hold (B) is too drastic for a one-week shift. Having the team work overtime to beat the freeze (C) violates the spirit of the freeze policy. The sponsor ignoring a systemwide freeze (D) would be a governance violation and is highly unlikely in a well-run organization.

Topics

#change control board#production freeze#schedule management#change management

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice