nerdexam
CompTIA

PK0-004 · Question #1026

A project manager is reviewing an update to a document that details the features of a planned solution. Additional features have been included for the marketing department. This is an example of:

The correct answer is C. a requirements change. Adding new features to a planned solution-specifically for the marketing department-is a requirements change. Requirements documents define the features and functionality the solution must deliver, so adding features means the requirements have changed. A quality change (A)…

Project management concepts

Question

A project manager is reviewing an update to a document that details the features of a planned solution. Additional features have been included for the marketing department. This is an example of:

Options

  • Aa quality change
  • Ba resource change
  • Ca requirements change
  • Da risk event

How the community answered

(28 responses)
  • B
    7% (2)
  • C
    89% (25)
  • D
    4% (1)

Explanation

Adding new features to a planned solution-specifically for the marketing department-is a requirements change. Requirements documents define the features and functionality the solution must deliver, so adding features means the requirements have changed. A quality change (A) would relate to standards or acceptance criteria. A resource change (B) would involve personnel or materials. A risk event (D) would represent an uncertain threat or opportunity-adding new features is a deliberate scope/requirements modification, not a risk event.

Topics

#requirements change#scope management#change control#feature addition