PK0-004 · Question #1014
PK0-004 Question #1014: Real Exam Question with Answer & Explanation
The correct answer is C: Resources. The triple constraint (and its extensions) includes scope, schedule, cost/budget, quality, and resources. Authorizing overtime directly impacts the Resources constraint - team members are being asked to work beyond normal hours, which affects their availability, energy, and cost
Question
Options
- AQuality
- BScope
- CResources
- DDeliverables
Explanation
The triple constraint (and its extensions) includes scope, schedule, cost/budget, quality, and resources. Authorizing overtime directly impacts the Resources constraint - team members are being asked to work beyond normal hours, which affects their availability, energy, and cost to the project. While budget is also affected (overtime pay), the direct constraint being stretched is the resource itself (human capital). Scope and quality are not directly changed by overtime; deliverables are what the project produces, not a constraint. Resources - the people doing the work - bear the direct burden of overtime.
Community Discussion
No community discussion yet for this question.