PK0-004 · Question #1006
PK0-004 Question #1006: Real Exam Question with Answer & Explanation
The correct answer is D: Project sponsor. The project sponsor holds the highest approval authority on a project. The sponsor provides funding, champions the project at the executive level, approves the project charter, authorizes major changes, and resolves escalated issues that fall outside the project manager's authori
Question
Options
- AProgram manager
- BProject manager
- CProject management office
- DProject sponsor
Explanation
The project sponsor holds the highest approval authority on a project. The sponsor provides funding, champions the project at the executive level, approves the project charter, authorizes major changes, and resolves escalated issues that fall outside the project manager's authority. The project manager (B) manages day-to-day execution but operates within the authority delegated by the sponsor. The PMO (C) provides governance, standards, and oversight, but does not own project authority. The program manager (A) manages a group of related projects, but authority at the individual project level still rests with the sponsor.
Community Discussion
No community discussion yet for this question.